Reference dates for payment claims involving draft claim regimes

Articles, Construction + Projects, ERA Legal News

Are draft claim regimes void in NSW?

It is not uncommon for a contract to set out a regime for progress payments which requires the builder to provide a “draft” of its progress claim for consideration before a “formal” claim for progress payment is provided.

Those contractual provisions may have the effect of excluding or modifying the effect of the Building and Construction Security of Payment Act 1999 (NSW) and therefore, may be void.

This article is important for those who entered contracts before 21 October 2019.

In the judgment of East End Projects Pty Ltd v GJ Building and Contracting Pty Ltd [2020] NSWSC 819, the Supreme Court considered whether a contractual regime which involved the use of draft progress claims was void under the Security of Payment Act.

The “draft claim regime” in East End

In this case, the developer applied to set aside an adjudication determination made in favour of the builder.  The developer asserted that the claim was not made in relation to a “reference date”.

The dispute involved a contract that was entered prior to 21 October 2019.  The post-21 October 2019 amendments to the Security of Payment did not apply to this dispute.

The contractual regime governing claims was as follows:

  1. The builder was to send a draft claim for progress payment to the Superintendent on or before the 25th day of each month, for work done to the last day of that month.
  2. The draft claim was required to provide detail of the work undertaken.
  3. The Superintendent was required to issue a “preliminary assessment” of the draft progress claim within 5 business days of receiving it.
  4. The builder was required to submit its formal progress claim not earlier than 7 business days after it submitted its draft claim.
  5. The contract specified that “reference dates” under the Security of Payment Act arose on the 7th business day after the draft progress claim had been submitted.

Reference dates under s. 8(2)(a) or s. 8(2)(b)?

The builder served a (formal) payment claim on the 28th of the month without serving a draft payment claim on the Superintendent.

The builder contended that the contractual regime that created reference dates modified the Security of Payment Act and were void by operation of s. 34 of the Security of Payment Act.  The Builder asserted that a reference date arose under s. 8(2)(b) (as it was prior to 21 October 2019) of the Security of Payment Act – that is, on the last day of each month.

The Queensland authority: Lean Field

The Builder relied upon the judgment in Lean Field Developments Pty Ltd v E & I Global Solutions (Aust) Pty Ltd [2016] 1 Qd R 30; [2014] QSC 293 where a similar contractual regime requiring draft progress claims was considered.  In Lean Field the formal claim would relate to a period of work that was different to that identified in the draft claim.

In Lean Field, the Queensland Supreme Court held that the relevant contractual terms that created “reference dates” were invalid because they excluded or modified the effect of the Building and Construction Industry Payment Act 2004 (Qld) (now repealed).

In Lean Field, the Court stated that a draft payment claim regime may be different if that regime involved service of a “draft” claim and a “formal” claim in relation to the same period of work – on the basis that, such a regime would allow the claimant to refine and correct its draft payment claim in light of the preliminary assessment.

In East End, the developer submitted that the clauses that created reference dates were not void / invalid because the draft claim regime was “facilitative” – that is, that the draft and formal claim related to the same period of work.

The law on draft claims in NSW

In East End, Justice Ball found that even where the draft claim related to the same period of work as claimed in the formal claim, the creation of a reference date which was contingent on the service of a draft progress claim could not satisfy the requirements of s. 8(2)(a) of the Security of Payment Act (as it was then) because it (at [17]) “does not provide a date on which a progress claim may be made”.

The NSW Supreme Court stated that if reference dates under a Contract (entered after 21 October 2019) arise only after a builder submits a draft payment claim, by a particular date, that would be:

… a serious restriction on the right to make a progress claim and therefore a serious restriction on the operation of s. 8 of the Act.

The application to set aside the adjudication determination was unsuccessful.

Impact on stakeholders

Those in NSW who have draft claim procedures for progress payment in contracts entered prior to 21 October 2019 should take note that reference dates under the Security of Payment Act are likely to arise at the end of each month.

Of course, this will depend on the specific words used in the contract.

Enquiries

If you are using draft claim regimes and wish to understand your rights either as builder or developer, please get in touch with our Construction + Projects team by phone (9324 5300), email (construction@eralegal.com.au) or online below.

 

People

With the technical skills, diverse backgrounds and practical experience to match, our teams care about their clients.

Our Expertise

We have a strong reputation for providing specialist, market-leading advice in the practices we offer. Our teams are experts in their field and provide an unrivalled service to clients.

News

We want to share our knowledge with you. A collection of news and insights into those areas in which we specialise.

Resources

We offer a relevant, easy access platform that allows clients and colleagues to gain access to relevant resources.

Contact Us

With offices in Sydney and Melbourne, our team pride themselves on always being available for their clients.

Careers

We are collaborative, respectful and inclusive. Recruiting the best talent is only half of the equation; providing a culture that enables development is the other.

See our exciting opportunities available for graduates, lawyers, legal support staff and business services professionals.