Challenging adjudication determinations in Court – when is an error a “jurisdictional error”?

Articles, Construction + Projects

Setting aside an adjudication determination

Since 1999, the Supreme Court and Court of Appeal in New South Wales have gradually eroded the scope for seeking judicial review of adjudication determinations made under the Building and Construction Industry Security of Payment Act 1999 (NSW).

An adjudication determination may be “set aside” (quashed) by the Supreme Court where it is found that the adjudicator made a “jurisdictional error” in making the determination.

If the Court find there was a jurisdictional error, the Court has the discretion to make various different orders – including:

  1. quash the determination completely,
  2. sever from the determination the parts which are affected by the jurisdictional error;
  3. quash part of the determination without affecting the balance; or
  4. quash the determination (or parts of it) and remit the dispute to the adjudicator so it can be re-determined by the adjudicator.

In Acciona Infrastructure Australia Pty Ltd v Chess Engineering Pty Ltd (No. 2) [2020] NSWSC 1788, the Supreme Court revisited the factors that it will consider in making orders about an adjudication determination that is infected by a jurisdictional error.

The error

In an earlier Supreme Court application, Acciona (the Respondent) sought to quash a determination in favour of the Chess (the Claimant) in the amount of $640,593.69 on the basis that there was a jurisdictional error in the determination.

The Respondent argued there were a number of jurisdictional errors.  The only error that was proven related to a variation and a disputed amount of $2,470.  The relevant part of the determination stated:

In neither the Payment Schedule nor the [Adjudication Response], [Acciona] does not direct me to any provision in the [statement of works] or elsewhere in the [sub-contract] which says that project management costs, overheads and profits are deemed to be included in the 15% loading already applied. In the [Adjudication Response] submissions, [Acciona] says it has received no verification of the hours involved. That reason was not proffered in the Payment Schedule.

I am satisfied that, for the purposes of an interim payment under the [SoP] Act, [Chess Engineering] is entitled to be paid the full amount claimed: $22,586.00.

The Court found in the earlier application that the adjudicator erred by failing to state reasons for how he came to be satisfied that the claimant was entitled to be paid the full value of the claimed amount for V17.

It followed that the Court determined that the adjudicator did not fulfil his requirement under the Security of Payment Act to determine the value of V17.  This was described as the adjudicator going “beyond jurisdiction” (at [207], Acciona v Chess (No. 1)).

The Court deferred making final orders to allow submissions to be made about the appropriate orders that should be made.

What is a “jurisdictional error”?

Concept of “materiality”

The Court was required to determine whether the error was a “jurisdictional error” that infected the determination.  A “jurisdictional error” in a determination must exist in order for the Court to quash a determination.

The concept of “materiality” and proportionality were a critical factor in the Court’s consideration of whether a jurisdictional error infected the determination.  Henry J said: (Acciona v Chess (No. 2) at [38])

In my view … the SoP Act should be interpreted as incorporating a threshold of materiality in the event of non-compliance by an adjudicator in undertaking their statutory task of determining the amount and timing of a progress payment such that legal force and effect should not be denied to a decision made in the event of every error in undertaking that task …

The concept of materiality was described as being a question of “whether an error results in a decision lacking the characteristics necessary for it to be given force and effect by the SoP Act and whether the error is sufficiently insignificant that it could not have materially affected the decision that was made.” (Acciona v Chess (No. 2) at [46]).

Was the “error” material to the determination?

As noted above, the error in Acciona v Chess was limited to a single variation dispute worth a very small fraction of the value of the determination.  The error did not impact on the balance of the determination. The Court described the error at [50] in Acciona v Chess (No. 2):

The Adjudicator’s error was that he failed to consider the merits and value of Chess Engineering’s claim in respect of the disputed amount of V17, one of many variations in respect of which the Adjudicator had many issues to decide. His error was made in the context where he stated in his reasons that he was satisfied of Chess Engineering’s entitlement to V17 in a conclusory way having considered and rejected Acciona’s submissions. The error was not part of a pattern of dealing with the disputes by the Adjudicator that reflected an overall failure by him to discharge his obligations under the SoP Act (judgment at [220]) but represented a failure that was out of line with his general approach.

The Court contrasted the error in Acciona v Chess against other errors, such as:

  • a failure to determine the amount of the progress payment due to a conclusion that the right to a progress payment was suspended under the contract: Parrwood
  • a determination made in respect of a payment claim that was not served in accordance with the Security of Payment Act: NSW Netball

The purpose of the comparison was to highlight that the Court had formed the view that the error in Acciona v Chess was not material.

The Court went on to say that the “nature, gravity and effect of the error did not work practical injustice sufficient to vitiate the Determination” (Acciona v Chess (No. 2), at [54]).

Finding: no jurisdictional error infected the determination

The Court stated that the Security of Payment Act permitted minor slips or mistakes to be corrected.  It was suggested that this was inimical of a legislative intent that errors in a determination in the nature of mistakes do not invalidate a determination (Acciona v Chess (No. 2) at [55]).

Having regard to the determination as a whole, the Court inferred that the adjudicator’s error arose from an “accidental or erroneous omission to value and assess the merits of the disputed part of V17, rather than a jurisdictional error that gives rise to invalidity of the whole of the determination” (Acciona v Chess (No. 2), at [56].

Given that the error might have led only to a very slight increase in the amount of the adjudication ($2,740), the nature, gravity and effect of the error did not work practical injustice sufficient to vitiate the determination.

It was found that the error was so insignificant that it did not materially affect the decision the adjudicator made.  The Court concluded that the determination was not infected by jurisdictional error.

Applying to set aside a determination after Acciona v Chess

A party who considers that there has been errors in an adjudication determination, even where those errors appear to be jurisdictional in nature, must also consider whether the error materially affected the decision of the adjudicator.

Not all determinations will have obvious jurisdictional errors, such as those seen in Parrwood and NSW Netball.  It is important to frankly assess a determination having regard to the principles in Acciona v Chess to determine whether it is commercially worthwhile applying to set aside an adjudication determination due to a “jurisdictional error”.  The criteria is whether the error is material to the determination.

If the error is not material and/or substantial, the case of Acciona v Chess suggests that caution should be exercised before applying to set aside a determination.

Questions?

If you have any questions about this article, please get in touch with our Construction + Projects team.  If you found this article interesting and want to learn more about the Security of Payment Act, read some of our recent articles:

People

With the technical skills, diverse backgrounds and practical experience to match, our teams care about their clients.

Our Expertise

We have a strong reputation for providing specialist, market-leading advice in the practices we offer. Our teams are experts in their field and provide an unrivalled service to clients.

News

We want to share our knowledge with you. A collection of news and insights into those areas in which we specialise.

Resources

We offer a relevant, easy access platform that allows clients and colleagues to gain access to relevant resources.

Contact Us

With offices in Sydney and Melbourne, our team pride themselves on always being available for their clients.

Careers

We are collaborative, respectful and inclusive. Recruiting the best talent is only half of the equation; providing a culture that enables development is the other.

See our exciting opportunities available for graduates, lawyers, legal support staff and business services professionals.